The construction of Almaty-Kapshagai auto-road of category A1, a strategically important object of the global development of the transport infrastructure of the Republic of Kazakhstan, began in August 2014.
To date, all excavations have been carried out on the left side of the road from 45 to 53 km, with a volume of 150,000 m3, and a concrete covering for 8 km of the site.
On September 21, the SA Construction Group Company commissioned 8 km of the section on the left side of the road.
On the right side, earthworks began in August 2015 on a 4-kilometer section of the road.
Until the end of 2015, the SA Construction Group company plans to finish all work on the installation of pavement, including concrete covering.
Concrete road Almaty-Kapshagay
Almaty region
Concrete road Almaty-Kapshagay. Category A1
2,5 years
The final delivery of the road is scheduled for the first half of 2016.